Home Build Costs

Concrete Slab Calculator

Work out the concrete a slab, footing, round pier, post-hole or set of steps needs — volume in cubic yards and cubic feet, 40/60/80 lb bag counts, and the ready-mix order.

Your pour

What are you pouring?

4 in for a patio or shed floor; 5–6 in for a driveway or garage.

A planning margin for spillage and over-dig. 5–10% is usual.

Premix bag
Inputs are kept in the page link

Try a worked example

What to buy

Ready-mix delivery

1.50yd³

1.15 m³. Rounded up to the 0.25 yd³ increment, at least the 1.00 yd³ minimum.

or premix bags

62× 80 lb

4,960 lb of dry mix to carry and mix. A delivery usually makes sense past about 23 bags.

1.23 yd³ sits in the slab before waste; both figures include 10% extra. Buy one route or the other, not both.

In the slab, before waste1.235 yd³
The same, in cubic metres and cubic feet0.944 m³ · 33.33 ft³
With 10% extra1.358 yd³ · 36.67 ft³
The order sits over the slab by0.27 yd³
Footprint100 ft²
One cubic yard covers, at 4.0 in81 ft²

Slab

drawn to the entered proportions
Shape diagramPlan view of a 10 ft by 10 ft rectangle, 4 inches thick, drawn to the entered proportions.
How it's calculatedShow
  1. 1

    Volume in the slab

    V = L × W × T

    10.00 × 10.00 × 0.3333 = 33.33 ft³ = 1.235 yd³

    Thickness 4.00 in ÷ 12, carried as a decimal of a foot and never rounded on the way through.

  2. 2

    Add the extra for spillage

    V′ = V × (1 + extra)

    33.33 × 1.10 = 36.67 ft³ = 1.358 yd³

  3. 3

    Premix bags

    bags = ⌈ V′ ÷ yield per bag ⌉

    ⌈ 36.67 ÷ 0.60 ⌉ = 62 bags

    Rounded up to whole bags. Yield per 80 lb bag from the Quikrete Concrete Mix No. 1101 data sheet (constants register).

  4. 4

    Ready-mix order

    order = max( minimum, round up V′ to the increment )

    max( 1.00, roundUp( 1.358, 0.25 ) ) = 1.50 yd³

    The increment and the minimum are supplier ordering conventions, set per region in the packaging layer — not engine constants.

1.50 yd³ ready-mixor 62 × 80 lb bags1.23 yd³ in the slab10% extra
1.23 cubic yards in the slab, before waste. To buy: 62 bags of 80 lb mix, or order 1.50 cubic yards of ready-mix. 10% waste applied.

About the concrete slab calculator

Concrete is a poured volume, not a unit count. The calculator takes the shape you pick, works out the volume it holds in full precision, adds a waste allowance, and then reports two ways to buy that volume — whole bags of dry mix, or a ready-mix delivery rounded to how a supplier actually sells it. Every formula and every constant it uses is below, each with the source it came from.

The "in the slab" figure is the geometry, before any waste — it is what the forms will hold if nothing spills, nothing over-digs and the subgrade is dead level. It is shown so you can check it against your own measurements — it is not the amount to buy.

The bag count and the ready-mix order are what to buy, waste included — both already carry the waste allowance and both are rounded up — bags to a whole bag, ready-mix to the supplier's increment and minimum. Ordering either figure as shown is ordering enough.

Pick one route, not both — the two lines are alternatives — 62 bags of dry mix or a 1.5-yard delivery for the same pour, not 62 bags plus a truck. Bags suit a small pour you can mix as you go; ready-mix suits anything a wheelbarrow would make miserable.

A small pour often orders more than it needs — if the ready-mix figure jumps to a round yard for a job that works out to a third of one, that is the supplier minimum, not a mistake. Below roughly a yard, most suppliers charge a short-load fee or will not deliver, so the order is set at the minimum they will bring.

For an odd shape, add the pieces — an L-shaped slab is two rectangles; a thickened-edge slab is a slab plus its perimeter footing. Run each piece through the matching shape, then add the volumes — the bag and order figures scale with the total.

This is a quantity, not a quote — the volume and the bag count are the durable part of planning a pour. What the concrete costs — per yard, delivered, or poured and finished — changes by region and by week, and is answered on the cost calculator, not here.

How to calculate concrete for a slab or footing

A rectangular slab or footing holds length × width × thickness, all measured in feet. Divide that cubic-foot figure by 27 to get cubic yards, because a yard is three feet and 3 × 3 × 3 = 27. A 10 ft × 10 ft slab at 4 inches — which is one third of a foot — is 10 × 10 × 0.3333 = 33.33 cubic feet in the slab, or 33.33 ÷ 27 = 1.23 cubic yards, before any waste.

The order the multiplication happens in does not matter, and that is the built-in check: area × thickness must equal length × width × thickness to full precision. If the two disagree, a dimension was entered in the wrong unit. The calculator computes it both ways on every keystroke and the diagram redraws to the proportions you entered.

Thickness is carried as a decimal of a foot, never rounded on the way through. This matters because the number gets multiplied twice more — once by the waste factor, once by a bag yield — and a value rounded early drifts by a bag or two by the end. The only rounding is at the very end, when whole bags and a supplier-sized order are what you can actually buy.

volume_ft³  = length_ft × width_ft × thickness_ft
volume_yd³  = volume_ft³ ÷ 27

  10 ft × 10 ft slab, 4 in thick (0.33333 ft):
  10 × 10 × 0.33333        = 33.333 cu ft   in the slab
  33.333 ÷ 27             =  1.235 cu yd   in the slab

How much one cubic yard covers

One cubic yard of concrete covers about 81 square feet at 4 inches thick, 65 square feet at 5 inches, and 54 square feet at 6 inches. The rule is 27 ÷ thickness in feet: at 4 inches, 27 ÷ 0.3333 = 81. Thicker slab, less area per yard — which is why the coverage figure on the page moves the moment you change the thickness.

Bag coverage follows the same rule from the bag's own cubic-foot yield. An 80 lb bag yields 0.60 cubic feet, so at 4 inches it covers 0.60 ÷ 0.3333 = 1.8 square feet. That is the arithmetic behind "how many bags for a 10 × 10 slab" — it is the slab's square footage divided by the per-bag coverage, then rounded up.

coverage_ft²_per_yd³ = 27 ÷ thickness_ft

  4 in : 27 ÷ 0.3333 = 81 sq ft per cubic yard
  5 in : 27 ÷ 0.4167 = 65 sq ft per cubic yard
  6 in : 27 ÷ 0.5000 = 54 sq ft per cubic yard

Bags, ready-mix, and where one stops making sense

The bag count is the poured volume in cubic feet, times one plus the waste percentage, divided by the bag's yield, then rounded up to a whole bag. You buy whole bags and you round the breakage allowance up, so the ceiling is right here — it is not a display rounding feeding back into a calculation, it is the number of bags that leave the store. One cubic yard takes 45 × 80 lb bags, 60 × 60 lb bags, or 90 × 40 lb bags.

The ready-mix order starts from the same post-waste volume in cubic yards, then rounds up to the supplier's increment — commonly a quarter or a half yard — and finally takes whichever is larger, that figure or the supplier's minimum load. Many US suppliers will not deliver below roughly one cubic yard without a short-load charge, so a small pour often orders one yard even though it needs less. Both the increment and the minimum are regional facts the calculator is configured with, not something baked into the formula.

Bagged concrete is practical up to roughly half a cubic yard — about 23 × 80 lb bags. Past that, mixing by the bag is a lot of work for a pour that a truck would place in minutes, and ready-mix costs less per yard at volume. The calculator shows both routes side by side so the crossover is visible rather than assumed. What a delivery or a pour costs is the sibling page's job.

bags      = ceil( volume_ft³ × (1 + waste) ÷ bag_yield_ft³ )
order_yd³ = max( supplier_minimum ,
                 roundUpTo( supplier_increment ,
                            volume_yd³ × (1 + waste) ) )

  bags per cubic yard :  27 ÷ 0.60 = 45   (80 lb)
                         27 ÷ 0.45 = 60   (60 lb)
                         27 ÷ 0.30 = 90   (40 lb)

How much extra concrete to order

The default waste allowance is 10%. It is a planning margin for spillage, over-excavation, an uneven subgrade and the concrete left in the chute or the wheelbarrow — not a measured quantity, and adjustable from 0 to 25%. It is applied once, to the in-place volume, before the bag and order figures are worked out.

Waste appears as a separate line in the bill of materials rather than being silently folded into the totals, so the parts still add up to the order: in-place volume plus the waste allowance equals what you order. A pour with no spare is a pour that stops halfway, but the margin should be visible, not hidden inside a rounded-up number.

How thick a slab should be

A concrete slab is 4 inches thick for patios, shed floors and walkways, and 5 to 6 inches for driveways and garage floors that carry vehicles. Edges that carry a wall or a post are often thickened to 8 to 12 inches. Thickness sets both the volume and the coverage per yard, so changing it on the page recomputes everything.

A standard site-batched concrete mix is 1 part cement to 2 parts sand to 3 parts gravel by volume, which gives roughly 3,000 psi. Bagged concrete mix is pre-blended to a set strength — the QUIKRETE No. 1101 data sheet lists 4,000 psi at 28 days — so the ratio only matters when you are batching from raw materials. Mix ratio changes how you make the concrete, never how much of it you need. Reinforcing bar and mesh are a separate quantity, not covered on this page.

Slab, footing, pier, post-hole and stairs

Slab and footing are the same rectangular prism — length × width × thickness. A footing is just a slab that happens to be narrow and deep, and it can be repeated with the count field for a run of identical pads.

A round column or pier is π × radius² × height. Enter the diameter and the calculator halves it. A 12-inch tube 4 feet tall holds π × 0.5² × 4 = 3.14 cubic feet; three of them is 9.42 cubic feet, about 0.35 cubic yards in the tubes.

A post-hole is the hole's volume minus the post that sits in it. A 10-inch-wide hole 2 feet deep is π × 0.417² × 2 = 1.09 cubic feet; a nominal 4×4 post is actually 3.5 inches on a side, so it displaces 0.292² × 2 = 0.17 cubic feet, leaving 0.92 cubic feet of concrete per hole — a little over 1.5 × 80 lb bags. A post-hole is bagged by nature, so the calculator does not show a ready-mix line for it.

A flight of steps is a staircase cross-section — run × rise × (1 + 2 + … + n) for n uniform steps — times the width. A 3-step flight 4 feet wide with a 7-inch rise and an 11-inch run is 0.917 × 0.583 × 6 × 4 = 12.83 cubic feet, or 0.48 cubic yards in the steps. The same figure comes out of stacking three prisms of increasing height and adding them, which is the check the golden fixture runs.

slab / footing : length_ft × width_ft × thickness_ft
column / pier  : π × (diameter_ft ÷ 2)² × height_ft
post-hole      : (π × hole_radius_ft² × depth_ft) − (post_side_ft² × depth_ft)
stairs         : run_ft × rise_ft × (1 + 2 + … + n) × width_ft

How the rounding works

Concrete is a poured volume, not a unit count, so the "floor the in-place count" rule used for blocks does not apply here. Instead:

Slab, footing and pier volume carries full precision through the whole chain — length, width and thickness in feet; volume in cubic feet is area × depth; volume in cubic yards is that ÷ 27. Rounding happens once, at the point the number is displayed.

Bag count is volume in cubic feet × (1 + waste%) ÷ the bag's cubic-foot yield, then rounded up — you buy whole bags and round the breakage allowance up.

Ready-mix order is volume in cubic yards × (1 + waste%), rounded up to the supplier increment (¼ or ½ yard), then taken as the larger of that and the supplier's minimum viable order (many US suppliers will not deliver below about 1 yd³). Both the increment and the minimum are regional packaging facts, not engine constants; a region with no minimum uses 0. A post-hole emits no ready-mix line at all — the line's absence is the signal, never a zero-quantity line.

Waste is an adjustable input, default 10%, shown as a separate line in the bill of materials so the parts still sum to the order quantity.

An L-shaped slab or a stepped footing decomposes into rectangles and prisms; the parts are allocated so they sum exactly to the total.

Worked examples

Each example is a golden fixture: hand-computed before the engine was written, asserted by the test suite on every build, and loadable into the calculator above from the chips under the inputs.

Slab, standard: 10 ft x 10 ft x 4 in, 10% waste, 80 lb bags

Pour
Slab
Length
10 ft
Width
10 ft
Thickness
4 in
Extra for spillage
10%
Premix bag
80 lb (0.60 ft³)

Concrete volume
1.235 yd³
Concrete volume
0.944 m³
Concrete volume
33.33 ft³
Premix bags to buy
62 bags
Ready-mix order
1.50 yd³

Checked against: hand derivation, in cubic feet: 10 * 10 * 0.333333 = 33.333333; 33.333333 / 27 = 1.234568; 33.333333 * 1.10 = 36.666667; 36.666667 / 0.60 = 61.111; 33.333333 / 27 * 1.10 * 45 = 61.111; 1.234568 * 1.10 = 1.358025.

Slab, garage, non-round thickness: 20 ft x 24 ft x 5 in, 10% waste, 80 lb bags

Pour
Slab
Length
20 ft
Width
24 ft
Thickness
5 in
Extra for spillage
10%
Premix bag
80 lb (0.60 ft³)

Concrete volume
7.407 yd³
Concrete volume
5.663 m³
Concrete volume
200.00 ft³
Premix bags to buy
367 bags
Ready-mix order
8.25 yd³

Checked against: hand derivation, in cubic feet: 20 * 24 * 0.416667 = 200.000; 200.000 / 27 = 7.407407; 480 * 0.416667 = 200.000; 200.000 * 1.10 = 220.000; 220.000 / 0.60 = 366.667; 7.407407 * 1.10 = 8.148148.

Round piers: 12 in diameter x 4 ft, x3, 0% waste, 80 lb bags

Pour
Round pier
Diameter
12 in
Height
4 ft
How many
3
Extra for spillage
0%
Premix bag
80 lb (0.60 ft³)

Concrete volume
0.349 yd³
Concrete volume
0.267 m³
Concrete volume
9.42 ft³
Premix bags to buy
16 bags
Ready-mix order
1.00 yd³

Checked against: hand derivation, in cubic feet: 0.5 * 0.5 * 4 = 1; 1 / 2 = 0.5; 3.141593 * 3 = 9.424779; 9.424779 / 27 = 0.349066; 9.424779 / 0.60 = 15.708.

Post-hole, per hole: 10 in diameter hole x 24 in deep, nominal 4x4 post (3.5 in actual), 80 lb bags

Pour
Post-hole
Hole diameter
10 in
Hole depth
24 in
Post width (actual)
3.5 in
Extra for spillage
0%
Premix bag
80 lb (0.60 ft³)

Concrete volume
0.034 yd³
Concrete volume
0.026 m³
Concrete volume
0.92 ft³
Premix bags to buy
2 bags
Ready-mix order
none — bagged by nature

Checked against: hand derivation, in cubic feet: 0.416667 * 0.416667 * 2 = 0.347222; 3.141593 * 0.347222 = 1.090831; 0.291667 * 0.291667 * 2 = 0.170139; 1.090831 - 0.170139 = 0.920692; 0.920692 / 0.60 = 1.534.

Stairs: 3 steps, 4 ft wide, 7-in rise, 11-in run, 10% waste, 80 lb bags

Pour
Stairs
Rise per step
7 in
Run per step
11 in
Number of steps
3
Width
4 ft
Extra for spillage
10%
Premix bag
80 lb (0.60 ft³)

Concrete volume
0.475 yd³
Concrete volume
0.363 m³
Concrete volume
12.83 ft³
Premix bags to buy
24 bags
Ready-mix order
1.00 yd³

Checked against: hand derivation, in cubic feet: 0.916667 * 0.583333 * 6 = 3.208333; 3.208333 * 4 = 12.833333; 0.916667 * 0.583333 * 4 * 3 + 0.916667 * 0.583333 * 4 * 2 + 0.916667 * 0.583333 * 4 * 1 = 12.833333; 12.833333 / 27 = 0.475309; 12.833333 * 1.10 = 14.116667; 14.116667 / 0.60 = 23.528; 0.475309 * 1.10 = 0.522840.

Slab, metric: 5 m x 4 m x 100 mm, 5% waste, 25 kg bags

Pour
Slab
Length
5 m
Width
4 m
Thickness
100 mm
Extra for spillage
5%
Premix bag
25 kg (0.41 ft³)

Concrete volume
2.000 m³
Concrete volume
2.616 yd³
Premix bags to buy
181 bags
Ready-mix order
2.25 m³

Checked against: hand derivation, in cubic metres: 5 * 4 * 0.1 = 2.000000; 2.000000 * 1.05 = 2.100000; 2.100000 / 0.011609907 = 180.880; 2.100000 / 0.25 = 8.4 → 9 increments = 2.25.

Round piers, metric: 300 mm diameter x 1.2 m, x4, 10% waste, 30 kg bags

Pour
Round pier
Diameter
300 mm
Height
1.2 m
How many
4
Extra for spillage
10%
Premix bag
30 kg (0.50 ft³)

Concrete volume
0.339 m³
Concrete volume
0.444 yd³
Premix bags to buy
27 bags
Ready-mix order
1.00 m³

Checked against: hand derivation, in cubic metres: 3.141593 * 0.15 * 0.15 * 1.2 = 0.084823; 0.084823 * 4 = 0.339292; 0.339292 * 1.10 = 0.373221; 0.373221 / 0.014158423 = 26.360; 0.373221 / 0.25 = 1.49 → 2 increments = 0.50; max(1, 0.50) = 1.00.

Post-hole, metric: 250 mm hole x 600 mm deep, 90 mm post, 0% waste, 25 kg bags

Pour
Post-hole
Hole diameter
250 mm
Hole depth
600 mm
Post width (actual)
90 mm
Extra for spillage
0%
Premix bag
25 kg (0.41 ft³)

Concrete volume
0.025 m³
Concrete volume
0.032 yd³
Premix bags to buy
3 bags
Ready-mix order
none — bagged by nature

Checked against: hand derivation, in cubic metres: 3.141593 * 0.125 * 0.125 * 0.6 = 0.029452; 0.09 * 0.09 * 0.6 = 0.004860; 0.029452 - 0.004860 = 0.024592; 0.024592 / 0.011609907 = 2.118.

Questions

How much concrete do I need for a slab?

A concrete slab's volume is length × width × thickness in feet, divided by 27 for cubic yards. A 10 ft × 10 ft slab at 4 inches (one third of a foot) is 10 × 10 × 0.3333 ÷ 27 = 1.23 cubic yards in the slab. Add waste — 10% is typical — for the quantity to buy or order.

How many bags of concrete do I need for a 10×10 slab?

A 10 ft × 10 ft slab at 4 inches holds 33.33 cubic feet in the slab. Add 10% waste to get 36.67 cubic feet, then divide by 0.60 cubic feet per 80 lb bag: 61.1, rounded up to 62 bags to buy. The yard-route cross-check — 33.33 ÷ 27 × 1.10 × 45 — also gives 61.1, because neither route rounds mid-chain.

How many bags of concrete make a yard?

Divide 27 cubic feet by the bag's yield. An 80 lb bag yields 0.60 cubic feet, a 60 lb bag 0.45, and a 40 lb bag 0.30 — from the QUIKRETE No. 1101 data sheet. So one cubic yard takes 45 × 80 lb bags, 60 × 60 lb bags, or 90 × 40 lb bags. Apply the waste factor first, then round up to whole bags.

How many cubic yards of concrete do I need?

Cubic yards is cubic feet divided by 27, because a yard is 3 feet and 3³ = 27. Get the volume in cubic feet first — area × thickness in feet — then divide by 27 and add waste. Area × thickness and length × width × thickness must match; if they do not, a dimension is in the wrong unit.

How much does a yard of concrete cover?

One cubic yard of concrete covers about 81 square feet at 4 inches thick, 65 square feet at 5 inches, and 54 square feet at 6 inches. The rule is 27 ÷ thickness in feet: at 4 inches, 27 ÷ 0.3333 = 81. Bag coverage follows the same rule from the bag's cubic-foot yield.

How thick should a concrete slab be?

A concrete slab is 4 inches thick for patios, shed floors and walkways, and 5 to 6 inches for driveways and garage floors that carry vehicles. Load-bearing edges are often thickened to 8–12 inches. Thickness sets both the volume and the coverage per cubic yard, so the calculator recomputes on every change.

How big should a concrete footing be?

A rectangular footing's volume is length × width × depth; a round pier's is π × radius² × height. A 12-inch tube (radius 0.5 ft, 4 ft tall) holds π × 0.5² × 4 = 3.14 cubic feet — 0.12 cubic yards in the tube, or with 10% waste about 6 × 80 lb bags to buy.

How many bags of concrete for a fence post?

A post-hole takes the hole's volume minus the post's. A 10-inch hole 2 ft deep is π × 0.417² × 2 = 1.09 cubic feet; a nominal 4×4 post — actually 3.5 inches — displaces 0.292² × 2 = 0.17 cubic feet, leaving 0.92 cubic feet per hole, about 1.5 × 80 lb bags.

How many bags of concrete are on a pallet?

Bags per pallet varies by brand and bag size, and the retailer's product listing is the place to confirm it for the mix you are buying. It is a delivery and stacking detail, not part of the volume maths — the calculator gives you the total bag count, and how many pallets that is depends on your supplier's pallet.

Sources and constants

The formulas the page uses, the sources every constant comes from, and the full register with check dates.

V_slab   = L × W × T              V_pier  = π × (D ÷ 2)² × H
V_hole   = (π × r² − s²) × depth   V_steps = run × rise × n(n + 1) ÷ 2 × width
bags     = ⌈ V × (1 + extra) ÷ yield per bag ⌉
order    = max( minimum, round up V × (1 + extra) to the increment )
  1. QUIKRETE Concrete Mix No. 1101 Product Data Sheet, "YIELD" table ("An 80 lb (36.2 kg) bag yields approximately 0.60 ft³ (17 L)"), rev. October 202280 lb concrete mix bag yield · 60 lb concrete mix bag yield · 40 lb concrete mix bag yield · Bagged mix compressive strength — checked 2026-09-02
  2. Sakrete High-Strength Concrete Mix product sheet, Technical Data table ("25 kg | Canada | 0.41 ft3 | .012 m3"), ©202325 kg concrete mix bag yield (metric) · 30 kg concrete mix bag yield (metric) — checked 2026-10-08
  3. The Miller Group, Residential Concrete for House Projects, FAQ ("the minimum order size is 1m3 and you can order in increments of 0.25m3") — a regional supplier convention, confirm per regionReady-mix order increment and minimum (metric) — checked 2026-10-08
Constants register — 14 constants, each with its source and check date
ConstantValueSourceAs of
Cubic yard27 cu ft per cu ydDefinition — 1 yd = 3 ft, and 3³ = 27n/a
Volume identityarea × depth = L × W × DGeometry — computed both ways on every input; a mismatch means a dimension is in the wrong unitn/a
80 lb concrete mix bag yield0.60 cu ft per bag (→ 45 bags per cu yd)QUIKRETE Concrete Mix No. 1101 Product Data Sheet, "YIELD" table ("An 80 lb (36.2 kg) bag yields approximately 0.60 ft³ (17 L)"), rev. October 20222026-09-02
60 lb concrete mix bag yield0.45 cu ft per bag (→ 60 bags per cu yd)Same data sheet, "YIELD" table ("A 60 lb (27.2 kg) bag yields approximately 0.45 ft³ (12.7 L)")2026-09-02
40 lb concrete mix bag yield0.30 cu ft per bag (→ 90 bags per cu yd)Same data sheet, "YIELD" table ("A 40 lb (18.1 kg) bag yields approximately 0.30 ft³ (8.5 L)")2026-09-02
Bagged mix compressive strength4,000 psi at 28 days (2,500 psi at 7 days)Same data sheet, Table 1 — context only, not fed into any quantity2026-09-02
Ready-mix order increment¼ yd³ (some suppliers ½ yd³)Supplier ordering convention — a regional packaging fact resolved in lib/packaging/us.ts, not an engine constant; confirmed per region at buildn/a
Ready-mix minimum viable order≈ 1 yd³ (regional; 0 where a supplier sets none)Supplier short-load convention — a regional packaging fact; below it, suppliers apply short-load pricing rather than refusing the ordern/a
25 kg concrete mix bag yield (metric)0.41 cu ft per bag (0.0116 m³)Sakrete High-Strength Concrete Mix product sheet, Technical Data table ("25 kg | Canada | 0.41 ft3 | .012 m3"), ©20232026-10-08
30 kg concrete mix bag yield (metric)0.50 cu ft per bag (0.0142 m³)Same product sheet, Technical Data table ("30 kg | Canada | 0.50 ft3 | .014 m3")2026-10-08
Ready-mix order increment and minimum (metric)0.25 m³ increments, 1 m³ minimumThe Miller Group, Residential Concrete for House Projects, FAQ ("the minimum order size is 1m3 and you can order in increments of 0.25m3") — a regional supplier convention, confirm per region2026-10-08
Coverage at 4 in81 sq ft per cu ydDerived — 27 ÷ (4 ÷ 12); 81 × 0.3333 ft = 27 cu ft = 1 cu ydn/a
Default waste allowance10% (adjustable 0–25%)Planning convention for spillage, over-excavation and chute loss — an adjustable input, not a measured valuen/a
Nominal 4×4 post actual size3.5 in × 3.5 inUS softwood lumber dressing convention — a nominal 4×4 finishes at 3½ in; used for post-hole displacementn/a

Checked against references

This calculator carries 8 worked examples with hand-derived answers. They run in the test suite on every build, and you can run them here, in your browser, against the same engine the page uses.